Resource-constrained Project Scheduling with Time-of-Use Energy Tariffs and Machine States: A Logic-based Benders Decomposition Approach

Authors: Corentin JuvignyAntonín NovákJan MandíkZdeněk Hanzálek

Organizations: Czech Institute of Informatics, Robotics and Cybernetics, Czech Technical University in Prague, Jugosl´avsk´ych partyz´an˚u 1580/3, 160 00, Prague 6, Czech Republic

Abstract

In this paper, we investigate the Resource-Constrained Project Scheduling Problem (RCPSP) with Time-of-Use (TOU) energy tariffs and machine states, a variant of RCPSP for production scheduling, where energy price is part of the criteria and one highly energy-demanding machine can be in one of the following three states: proc, idle, or off. The problem involves scheduling all tasks, respecting precedence constraints and resource limitations, while minimizing the combination of the overall makespan and the Total Energy Cost (TEC), which varies according to the TOU tariffs, which can take negative values. We propose two novel approaches to solve it: a monolithic Constraint Programming (CP) approach and a Logic-Based Benders Decomposition (LBBD) approach. The latter combines a master problem handling the energy cost solved using Integer Linear Programming (ILP) with a subproblem handling the RCPSP, resolved using CP. Both approaches outperform the monolithic compact ILP counterpart, but the LBBD significantly outperforms the monolithic CP in most cases, especially when the makespan criterion is not included in the objective function, solving to optimality instances with up to 480 tasks. Finally, we propose a way to generalize our LBBD approach to other problems sharing similar characteristics, and applied it to various problems, such as an RCPSP with blocking times & total weighted tardiness criterion, or a flexible job shop.

Explore similar work

May 15, 2026cs.AI

Petri Net Induced Heuristic Search for Resource Constrained Scheduling

We formulate the Resource-Constrained Project Scheduling Problem (RCPSP) as optimal search over the reachability graph of a Timed Transition Petri Net with Resources, using relative-delay tokens so that scheduling decisions correspond to transition firings in the induced state space. We solve the resulting problem with AA^* guided by a heuristic that combines Critical Path and resource-based lower bounds, and prove that it is consistent under our token-based time semantics. Experiments on the PSPLIB benchmarks show that the approach outperforms strong exact Mixed-Integer Linear Programming (MIP) baselines (SCIP, CBC) in both success rate and solve time. Per-instance analysis shows that heuristic search and MIP degrade along independent axes, resource tightness for AA^* and formulation size for MIP, with resource strength mediating which solver benefits from scale.
Ido Lublin, Dor Atzmon, Izack Cohen
May 14, 2026cs.AI

PyCSP3-Scheduling: A Scheduling Extension for PyCSP3

PyCSP3^3 provides a productive way to build constraint models for solving combinatorial constrained problems and export them to XCSP3^3, preserving a complete separation between modeling and solving. However, it lacks native support for scheduling abstractions such as interval variables, sequence variables, and resource functions. As a result, scheduling models must be encoded with low-level integer variables and manual channeling constraints, even though PyCSP3^3 already provides global constraints like NoOverlap and Cumulative on integer arrays. We present PyCSP3^3 Scheduling, a library that adds scheduling abstractions to PyCSP3^3 through 53 dedicated constraints and 27 expressions, and compiles them down to standard PyCSP3^3/XCSP3^3 constraints, maintaining the modeling/solving separation that underpins the PyCSP3^3 ecosystem. On 261 paired instances across 17 model families (5 runs each), both formulations produce identical objectives on all 72 doubly-proved optimal pairs and nearly half of the families (8/17) remain structurally unchanged after compilation; however, runtime performance diverges across families, with clear gains on some (up to 5.8x) and regressions on others due to the overhead of compilation decompositions. Code and benchmarks are available at: https://github.com/sohaibafifi/pycsp3-scheduling
Sohaib Afifi
May 22, 2026cs.AI

CP or DP? Why Not Both: A Case Study in the Partial Shop Scheduling Problem

Dynamic Programming (DP) and Constraint Programming (CP) are well-established paradigms for solving combinatorial optimization problems. Usually, these two approaches are used separately. This paper aims to show that the two can be combined effectively and elegantly, with DP serving as the primary search framework and CP used as a subroutine to leverage global constraint propagation. This paper presents such an approach for the Partial Shop Scheduling Problem (PSSP), for which a pure DP method has previously been proposed, and efficient CP filtering algorithms are available. The PSSP is a general scheduling problem where each job consists of a set of operations with arbitrary precedence constraints. The approach is flexible enough to accommodate anytime DP strategies, such as anytime column search, whereas the original DP algorithm operated in a strictly layer-wise manner. Moreover, the flexibility of the CP modeling makes it straightforward to incorporate arbitrary precedence constraints. As a result, the model naturally handles any precedence graph and even enables the design of a Large Neighborhood Search (LNS) scheme, in which the DP model is reused, and partial-order schedules are imposed across restarts to improve the incumbent solution. While not competitive with state-of-the-art pure CP solvers for this specific problem, our primary contribution is demonstrating the viability of this hybrid integration.
Emma Legrand, Roger Kameugne, Pierre Schaus