Unlocking Heterogeneous Accelerator Flexibility in AI Data Centers: Sizing and Workload Allocation

Authors: Chenghao Lyu, Ying Yu, Wangkun Xu, Fei Teng

Organizations: Department of Electrical and Electronic Engineering, Imperial College London, London, UK

Abstract

AI data centers are an emerging electricity demand, but limited local grid capacity could delay their connection and expansion. While existing operational strategies consider spatio-temporal workload flexibility, few studies address the strategic sizing and allocation of diverse accelerator archetypes with different capital and energy-efficiency trade-offs. This paper unlocks the flexibility potential of heterogeneous accelerators by jointly sizing and allocating different AI workloads (training, delay-tolerant batch work, and online inference requests) across sites and hours to meet the time-varying grid constraint at minimum cost. Workload-specific throughput and energy coefficients link these decisions to facility power. In a representative two-site case, heterogeneous sizing reduces daily cost by 6.5% relative to spatio-temporal scheduling with fixed capacity. When evaluated using workload-specific performance, a capacity design based on workload-averaged hardware coefficients costs 7.7% more than the proposed design. The proposed design also eliminates the envelope violations of an unconstrained design at a 0.25% daily cost increase. These results show how hardware heterogeneity and workload flexibility jointly shape economical, grid-compliant capacity plans.

Figures & tables

Explore similar work

Jun 23, 2026

Power-Flexible AI Data Centers: A New Paradigm for Grid-Responsive Compute

The rapid expansion of artificial intelligence (AI) infrastructure is driving unprecedented growth in electricity demand from data centers. Traditional power-system planning treats large computing facilities as inflexible peak loads, leading to costly infrastructure upgrades and long delays in grid interconnection. Recent work has shown that AI clusters can reduce electricity consumption during peak demand through software-based workload orchestration. This article explores how modern GPU-based AI data centers can operate as grid-interactive assets that respond dynamically to power system conditions. We describe an architecture integrating grid signals, workload scheduling, and power telemetry for fine-grained cluster power control. Experimental results from a real-world deployment on a 130 kW GPU cluster demonstrate multiple forms of flexibility, including rapid load reduction, sustained curtailment, and carbon-aware operation while preserving service levels for priority jobs. We further demonstrate performance-aware load shifting across geographically distributed clusters, enabling workloads to migrate toward regions with lower grid stress. Together, these capabilities transform AI infrastructure from static electricity consumers into flexible resources that support grid reliability, accelerate interconnection, and improve computing sustainability.
May 15, 2026

Designing Datacenter Power Delivery Hierarchies for the AI Era

Demand for AI accelerators is rapidly increasing rack power density, with projections approaching 1MW per deployment by 2027. This poses a major challenge for datacenter power delivery designers. As power densities increase, a datacenter designed for a different target density may strand power, i.e., may be unable to use all the power that its delivery hierarchy has provisioned. Designs must remain efficient over long datacenter lifetimes and multiple hardware generations. Power utilization is particularly important as grid power capacity is a scarce resource in the AI era. Designing an efficient power delivery hierarchy for the long run is difficult because rack placement feasibility, workload impact, and cost depend jointly on electrical topology, deployment granularity, placement policy, power oversubscription, and workload mix. Moreover, each of these factors evolve over time, have inter-dependencies across multiple resource dimensions, and generally do not lend themselves to closed-form analysis. To address this challenge, we develop a framework for evaluating datacenter power delivery designs using throughput, power, and cost metrics over realistic arrival, oversubscription, and decommissioning sequences. The framework combines projection models for GPU, compute, and storage deployments with operational factors grounded in production data from Microsoft Azure. Our results show that multi-resource stranding materially changes deployable capacity, effective capital expenditure, and delivered performance, and quantify how rising density from rack- and pod-scale AI systems shapes these outcomes. For AI datacenter design, the relevant planning objective is not installed megawatts, but deployable capacity over time.
May 4, 2026

From Barrier to Bridge: The Case for AI Data Center/Power Grid Co-Design

For over a century, the electric grid has relied on a single statistical assumption: load diversity, the principle that the uncorrelated demands of millions of small consumers produce a smooth, predictable aggregate. AI training data centers break that assumption. A single hyperscale training campus can draw power comparable to a mid-sized city, driven by one tightly synchronized job whose demand swings by hundreds of megawatts in seconds. This paper argues that the resulting entanglement of compute and power infrastructure requires a shift from implicit coexistence to explicit co-development between the historically decoupled data center and electric power industries. We introduce the distinct design principles, operational philosophies, and economic incentives of each sector, and show why their cultural and technical misalignment makes coordination difficult. We identify key research directions, from joint capacity planning, multi-timescale control, a compute--power protocol stack, to market innovation, that must be pursued to power the future of AI sustainably and reliably.