Autonomous agents for electricity-system planning
Organizations: Department of Nuclear, Plasma, and Radiological Engineering, The Grainger College of Engineering, University of Illinois Urbana-Champaign, Urbana, IL, USA. · Department of Applied Mechanics, Indian Institute of Technology Delhi, New Delhi, India. · Yardi School of Artificial Intelligence, Indian Institute of Technology Delhi, New Delhi, India. · National Center for Supercomputing Applications, University of Illinois Urbana-Champaign, Urbana, IL, USA.
Abstract
Planning electricity systems requires repeated decisions that connect regional resources, investment, operation and network constraints. Here we present an autonomous planning framework that carries prepared regional scenarios through proposal, numerical evaluation, feedback interpretation, redesign and final plan selection. Agents propose investment bounds, storage operating conditions and feeder interventions, interpret numerical feedback, and decide how to revise designs and when to stop. The framework automatically executes annual investment-and-dispatch optimization and representative-feeder verification, applies fixed acceptance criteria and retains the lowest-cost accepted candidate. We evaluate forty carbon-constrained trajectories across ten system-year scenarios in five electricity systems and four countries, using two model deployments and single- and multi-agent architectures. All forty retain candidates satisfying the implemented physical and fixed annual operational carbon-budget checks. Twenty-eight of forty matched reference designs exceed the new scenario ceilings. A separate archive of ninety-six trajectories under a common 1,000 Mt annual ceiling provides matched references and broader regional coverage. The results demonstrate autonomous planning under explicit emissions constraints using public regional data and published institutional demand outlooks.
Figures & tables
| Study | Planning decision addressed | Scope demonstrated |
| Electricity-system studies in Nature Energy | ||
| Zhu et al. [ 5 ] | How much generating capacity is needed to meet global electricity needs under net-zero pathways? | Joint capacity expansion and hourly operation in a spatially resolved global model. |
| Few et al. [ 6 ] | Where can local flexibility reduce network upgrades? | Network simulations quantify how upgrade costs and the value of flexibility vary across Great Britain. |
| Beiter et al. [ 10 ] | How much offshore wind is built under different planning assumptions? | US expansion scenarios quantify deployment across cost, transmission and policy assumptions. |
| Senga et al. [ 11 ] | Where should interregional transmission expand? | US expansion strategies are compared on cost, emissions and reliability during extreme events. |
| Liang et al. [ 12 ] | Where does heat limit grid capacity? | Weather-dependent demand and equipment limits reveal transmission bottlenecks in western Europe. |
| System | Capacity | Expert plan | Carbon range | Difference |
|---|---|---|---|---|
| Brazil | Wind | 49.55 | 120.19 | +70.64 |
| Brazil | Solar † | 29.19 | 96.66 | +67.47 |
| Brazil | Battery power | 6.63 | 0.00 | -6.63 |
| South Africa | Wind | 26.39 | 5.57–6.24 | |
| South Africa | Solar † | 21.16 | 63.02–64.24 |
| System | Units | Demand basis |
|---|---|---|
| MISO | 6 | EIA-930 hourly observations, grouped LRZs |
| ERCOT | 8 | EIA-930 hourly observations, weather zones |
| NYISO | 11 | EIA-930 hourly observations, zones A–K |
| South Africa | 10 | ESRG reference scenario, corrected supply-area hourly profiles |
| Australia (NEM) | 5 | AEMO five-minute regional TOTALDEMAND from price-and-demand records, averaged to hourly |
| New Zealand | 5 | EMI metered grid offtake by point of connection, summed to the five EMI zones |
| System | Corridors | Network basis | Candidate projects |
|---|---|---|---|
| NYISO | 12 | Directional transfer limits; five model cut-sets assembled from operating and reliability studies | Propel NY (1,300 MW into Zone K) |
| MISO | 7 | Zonal import/export limits; Midwest–South physical transfer limits 3,000/2,500 MW | LRTP Tranche 1 and 2.1 lines, segments of one project bundled |
| ERCOT | 17 | Fixed study limits of 12,240 MW for West Texas Export and 5,595 MW for North-to-Houston | Permian 765 kV import paths and STEP eastern backbone; aggregate STEP increment assigned as described below |
| South Africa | 21 | NTCSA line GIS aggregated to supply areas; ratings estimated using the PyPSA-RSA method [ 39 , 40 ] | 31 inter-area candidates extracted from the TDP |
| Australia | 5 | Static directional capabilities from AEMO’s archived September 2025 edition (v5) | VNI West, QNI Connect, Marinus Link stages 1/2 and EnergyConnect; ISP Appendix 5 |
| New Zealand | 4 | HVDC inter-island capability from the Transmission Planning Report 2023; island backbones as non-binding proxies | HVDC cable replacement and possible fourth-cable upgrade to 1,400 MW northward |
| System | Year | Budget (Mt yr -1 ) | Source basis |
|---|---|---|---|
| NYISO | 2023 | 24.761865 | New York RGGI base allowance budget |
| NYISO | 2030 | 12.425308 | New York RGGI base allowance budget |
| NYISO | 2035 | 3.550088 | New York RGGI base allowance budget |
| MISO | 2030 | 200.033343 | Future 2 aggregate planning constraint |
| MISO | 2035 | 164.641838 | Future 2 aggregate planning constraint |
| South Africa | 2030 | 168 | IRP 2025 balanced-plan emissions pathway |
| System | Demand 2023 | Demand 2030 | Change (%) | Demand 2035 | Change (%) |
|---|---|---|---|---|---|
| MISO | 640.968 | 868.579 | 35.5 | 961.187 | 50.0 |
| ERCOT | 446.802 | 983.792 | 120.2 | 1136.972 | 154.5 |
| NYISO | 146.997 | 160.160 | 9.0 | 170.170 | 15.8 |
| South Africa | 227.005 | 257.571 | 13.5 | 294.539 | 29.7 |
| Australia | 180.155 | 203.655 | 13.0 | 252.242 | 40.0 |
| New Zealand | 37.630 | 44.919 | 19.4 | 51.399 | 36.6 |
| Wind | Solar PV | |||||
|---|---|---|---|---|---|---|
| System | 2023 | 2030 | 2035 | 2023 | 2030 | 2035 |
| MISO | 0.321 | 0.255 | 0.271 | 0.168 | 0.202 | 0.204 |
| ERCOT | 0.339 | 0.256 | 0.245 | 0.179 | 0.211 | 0.210 |
| NYISO | 0.230 | 0.422 | 0.441 | 0.149 | 0.184 | 0.189 |
| South Africa | 0.252 | 0.228 | 0.218 | 0.201 | 0.205 | 0.206 |
| Australia (NEM) | 0.249 | 0.439 | 0.449 | 0.170 | 0.180 | 0.180 |
| Demand year | Weather source | Hourly template | Hourly index |
|---|---|---|---|
| 2023 | ERA5 2023 reanalysis | 2023 | 2023 |
| 2030 | NASA MPI-ESM1-2-HR SSP2-4.5, 2030 projection | ERA5 2023 | 2023 |
| 2035 | NASA MPI-ESM1-2-HR SSP2-4.5, 2035 projection | ERA5 2023 | 2023 |
Appendix figures & tables22 assets
Supplementary material from the paper’s appendix.
Appendix
| Setting | Claude Opus 5.5 |
|---|---|
| Inference | Anthropic Messages API |
| Completed trajectories | 16 for demand year 2023 |
| Single-agent ceiling | 120 turns; 40 committed evaluations |
| Multi-agent ceiling | 120 cycles |
| Default output ceiling | 16,000 tokens |
| Generation | Adaptive thinking; high effort; standard-only tier |
| Model | Demand and weather inputs | Completed cases |
|---|---|---|
| GPT-6.1 Sol | 2023 demand with ERA5 2023 weather; 2030 and 2035 demand with the corresponding NASA-derived weather | 48 |
| Claude Opus 5.5 | 2030 and 2035 demand with the corresponding NASA-derived weather | 32 |
| Deployment | Demand / weather | Single | Multi | Accepted | Total |
|---|---|---|---|---|---|
| GPT-6.1 Sol | 2023 / ERA5 | 8 | 8 | 16 | 16 |
| GPT-6.1 Sol | 2030 / NASA | 8 | 8 | 16 | 16 |
| GPT-6.1 Sol | 2035 / NASA | 8 | 8 | 16 | 16 |
| Opus 5.5 | 2023 / ERA5 | 8 | 8 | 16 | 16 |
| Opus 5.5 | 2030 / NASA | 8 | 8 | 16 | 16 |
| Opus 5.5 | 2035 / NASA | 8 | 8 | 16 | 16 |
| System | Selected cost | System evaluations | Model requests |
|---|---|---|---|
| MISO | 28.293256/28.293256 | 1/3 | 3/11 |
| ERCOT | 18.225239/18.225239 | 3/3 | 6/11 |
| NYISO | 8.030121/8.030121 | 2/3 | 5/21 |
| South Africa | 10.652093/10.656181 | 8/13 | 11/55 |
| Australia | 7.052820/7.052820 | 3/3 | 7/11 |
| New Zealand | 0.569150/0.569150 | 1/3 | 4/11 |
| System | GPT-6.1 Sol | Claude Opus 5.5 |
|---|---|---|
| MISO | 46.000616/46.145542 | 46.003694/46.003694 |
| ERCOT | 68.057741/68.076200 | 68.407019/68.407550 |
| NYISO | 6.477653/6.477653 | 6.477653/6.477653 |
| South Africa | 12.017688/12.019324 | 12.052166/12.020040 |
| Australia | 6.861099/6.861099 | 6.861099/6.861099 |
| New Zealand | 0.646734/0.646734 | 0.646734/0.646734 |
| System | GPT-6.1 Sol | Claude Opus 5.5 |
|---|---|---|
| MISO | 52.959760/53.216539 | 52.961390/53.216539 |
| ERCOT | 82.980096/82.957622 | 83.762708/83.150660 |
| NYISO | 6.829947/6.829947 | 6.829947/6.829947 |
| South Africa | 14.097805/14.098005 | 14.202359/14.101251 |
| Australia | 8.853329/8.854495 | 8.854495/8.854495 |
| New Zealand | 0.799669/0.799669 | 0.799669/0.799669 |
| Deployment/year | Committed | Verify | Responses | Median cycles |
|---|---|---|---|---|
| Sol 6.1 2023 | 62 | 29 | 398 | 1 |
| Sol 6.1 2030 | 91 | 50 | 578 | 1 |
| Sol 6.1 2035 | 91 | 53 | 517 | 1 |
| Opus 5.5 2030 | 41 | 29 | 254 | 1 |
| Opus 5.5 2035 | 46 | 41 | 290 | 1 |
| System | Selected cost | Evaluations | Responses |
|---|---|---|---|
| MISO | 28.293256/28.293256 | 3/3 | 9/12 |
| ERCOT | 18.225239/18.225239 | 3/3 | 9/11 |
| NYISO | 8.030084/8.030121 | 4/4 | 14/21 |
| South Africa | 10.647249/10.647689 | 7/25 | 23/149 |
| Australia | 7.052820/7.052820 | 4/3 | 12/11 |
| New Zealand | 0.569150/0.569150 | 3/3 | 9/11 |